Global gas turbine orders exceed production capacity, sending developers toward refurbished units and jet-engine-based power systems.
Worldwide gas turbine orders have topped 100 gigawatts, while estimated global production capacity is 60 to 70 gigawatts, according to Wood Mackenzie. Demand from AI data centres is driving utilities and developers to seek used, refurbished and jet-engine-based equipment.
In the United States, turbine delivery takes six years on average, Wood Mackenzie analyst Aurora Tenorio said. She said delivery discussions are focused on 2030 and 2031.
Used equipment can cost less than new turbines. Origin Partners managing partner Zach Machuca put prices for well-maintained used units at $1.5 million to $1.7 million per megawatt, and refurbished units at about $1.3 million. Aurora Energy Research estimates new turbines cost $2 million to $2.5 million per megawatt.
The secondary market cannot resolve the supply crunch on its own, Enverus Intelligence Research associate Noor Qureshi said. Used machines can have unclear maintenance records and limited remaining life, while jet-engine conversions raise questions about their suitability for continuous power generation.
Some developers are turning to alternatives. Crusoe ordered 13 jet-engine-based turbines from ProEnergy in April, with a combined capacity of 650 megawatts, for planned US data centre projects. Finland’s Wartsila has booked around 3 gigawatts of orders since spring last year for gas-engine power units serving US data centres, its energy business president said.
This article was produced with the help of AI technology. Based on reporting by the outlets listed above.