Skip to content
Markets News
AI & Tech1 min read

AI Data Center Plans Add 181GW of On-Site Gas Power

Makkler Newsroom
November 11, 2026 · Based on reporting by The Guardian
Photo: Victorgrigas / Wikimedia Commons · CC BY-SA 3.0

A BloombergNEF report says grid delays are driving plans for gas-fired power at data centers across the US, UK and mainland Europe.

Key takeaways

  • Plans across the US, UK and mainland Europe propose 181GW of on-site gas-fired capacity.
  • BloombergNEF estimates the US rollout would emit about 345 million metric tonnes of CO₂ equivalent annually.
  • AI data center electricity demand is forecast to reach 2,354 terawatt-hours by 2035.

Plans for on-site gas-fired power at AI data centers across the US, UK and mainland Europe total 181GW of capacity, according to BloombergNEF research. The report links the proposals to delays in connecting facilities to national grids.

About 90% of the planned on-site gas stations are in the US. If the plans go ahead, they would produce an estimated 345 million metric tonnes of carbon dioxide equivalent emissions a year there, BloombergNEF said.

The report forecasts that AI data center electricity demand will almost quadruple by 2035, reaching 2,354 terawatt-hours, or 7% of global electricity demand. BloombergNEF’s Mark Daly said the climate impact would depend partly on how quickly grids connect facilities and whether cleaner power is added.

In the UK, data centers made more than 100 inquiries about connecting to gas in 2024-25, according to Future Energy Networks. Two proposed sites, Wapseys Wood in Buckinghamshire and Quest Park in Bedfordshire, are seeking on-site gas stations while awaiting grid connections.

Developers describe the gas supply as temporary, but Daly warned that operators may keep generating power after grid connections arrive. The report says faster grid connections are a more sustainable option and could limit emissions and the risk of long-term reliance on fossil fuels.

The UK government has backed temporary on-site fossil fuel stations for data centers while they wait for grid access. Oliver Hayes of Global Action Plan criticized that support, saying the plants could lock in high emissions for years.

Topics
AMZNMSFTGOOGLMETAORCLAI Data CentersBloombergNEFGlobal Action Plan
Further reading

This article was produced with the help of AI technology. Based on reporting by the outlets listed above.

Comments (0)

Log in to join the discussion.Log in

No comments yet - be the first to weigh in.