The railmaker lowered its earnings and cash-flow forecasts after execution problems hit Coradia Max and other projects in Germany.
Alstom cut its fiscal 2026/27 adjusted EBIT margin forecast to around 1%, from about 6.5%, after project execution problems weighed on its preliminary first-half results. The company said the issues centered on its Coradia Max platform and projects executed for and from Germany.
For the six months ended September 30, sales rose 3% to €9.3 billion, including 2% organic growth. Adjusted EBIT margin was around negative 4%, compared with 6.4% a year earlier. Alstom produced 1,860 cars, down 8% from the prior-year period.
The company now expects full-year free cash flow of negative €1.5 billion, versus its previous forecast for positive free cash flow. It lowered expected car production to around 4,000 from 4,400 to 4,500, and now forecasts low- to mid-single-digit organic sales growth, down from about 5%. Its book-to-bill outlook remains above 1.
Alstom said technical issues and additional testing requirements affected Coradia Max production, while reviews of other projects identified execution risks and additional work. The company said extended approval timelines and later-than-expected commercial entry for major projects also affected its cash-flow outlook.
The board has begun reviewing options to reduce debt by around €2 billion by September 2027. Alstom is also reviewing its organisational and operational models, with key decisions expected by early 2027.
This article was produced with the help of AI technology. Based on reporting by the outlets listed above.