The partners approved construction in Namibia, with first uranium production targeted for 2028 and most lifetime output committed to CNNC.
Bannerman Energy and Chinese partner CNNC Overseas approved construction of the Etango uranium project in Namibia, with first production targeted for 2028. Development is expected to cost $353 million before production.
Bannerman said about $64 million has already gone toward early works, leaving roughly $289 million in pre-production spending. The project is expected to produce an average of 3.5 million pounds of uranium oxide a year.
CNNC Overseas invested $320.4 million under a September financing agreement, including $294.5 million in the joint venture. It will buy 60% of Etango’s lifetime production on market-based terms, while Bannerman retains marketing rights over the other 40%.
The venture had about $295 million in cash at Sept. 30 to cover remaining pre-production spending. Bannerman said it separately held about A$175 million to fund its share of working capital through construction, ramp-up and targeted commercial production.