Testing has begun on the Osmaneli-Bursa section, while the full project remains under construction and has no announced opening date.
Testing has begun on the Osmaneli-Bursa section of the Bandırma-Bursa-Yenişehir-Osmaneli high-speed rail project, Turkey’s Transport and Infrastructure Minister Abdulkadir Uraloğlu said. He said infrastructure and superstructure work on the section is complete.
Track geometry and static catenary measurements were completed in September and October, and signaling power-system tests began in October. November work includes hot running tests, dynamic acceleration tests and dynamic catenary measurements. Further signaling, safety and integration tests with the Ankara-Istanbul high-speed line are planned.
The full project is 83.08% complete, with construction continuing on the Bursa-Bandırma section. Uraloğlu said the project is intended to carry both passengers and freight. Once the Osmaneli-Bursa section is complete, the targeted journey time from Bursa to Istanbul and Ankara is 2 hours 15 minutes. No opening date has been announced.
This article was produced with the help of AI technology. Based on reporting by the outlets listed above.