The miner cut its annual production floor by 5,000 tonnes as full processing at its Arizona operation slips to mid-December.
Capstone Copper lowered the bottom of its annual copper production forecast by 5,000 tonnes, to 195,000 tonnes, after delaying Pinto Valley’s full restart until mid-December. The Arizona operation expects to resume partial processing with mobile crushers in mid-November.
The primary crusher needs more repairs to major components being made off-site by its original equipment maker, the company said. Capstone estimated the additional downtime would cut this year’s copper output by about 5,000 tonnes, depending on restart timing.
A national truckers’ strike in Chile is also threatening shipments of copper concentrate and cathode, as well as deliveries of fuel and sulphuric acid. Capstone said preventive measures and on-site storage had so far protected output at its two Chilean operations.
TD Securities analyst Craig Hutchison said the strike, combined with the Pinto Valley delay, introduced “incremental downside risk to year-end production.” Jefferies analyst Tariq Fahad called the production impact modest but said execution and operating reliability were bigger concerns.
Capstone shares closed Friday at C$10.23, down 4.75% on the session. They had fallen 6.5% on Thursday, according to the source article.