The miner reported lower cobalt production through September as it held more metal in solution and maintained its 2026 copper guidance.
Glencore produced 13,700 tonnes of its own-sourced cobalt in the first nine months of 2026, down 52% from a year earlier. The miner said Democratic Republic of Congo export quotas led it to leave more cobalt unprocessed.
Glencore is retaining cobalt in mixed ore in solution instead of converting it into saleable hydroxide, which the company said reduces near-term processing costs. It expects to recover the metal’s value as export rules evolve, but does not include the retained material in reported production.
The company said its Kamoto Copper Company and Mutanda operations have enough cobalt stocks to meet near-term export allocations. Glencore maintained its 2026 copper production guidance of 810,000 to 870,000 tonnes, while saying output is expected to finish near the bottom of that range.
Glencore shares traded at 535.5 pence, down 1.11% from the previous close, as of 14:39 UTC on Thursday.
This article was produced with the help of AI technology. Based on reporting by the outlets listed above.