The agency also expects emissions tied to data centers to rise 70%, while grid bottlenecks could delay projects.

Key takeaways

  • The IEA says data center electricity use could double by 2030 to about 1,000 terawatt-hours a year.
  • AI is expected to account for three-quarters of the growth in data center electricity use.
  • Emissions linked to data centers are projected to rise 70% by 2030.
  • The IEA warns grid constraints and tight supply chains could slow new data center projects.

Global data center electricity use could double by 2030 to around 1,000 terawatt-hours a year, the International Energy Agency said. AI is expected to account for three-quarters of the growth, while emissions linked to the sector could rise 70%.

The IEA expects the power mix to differ by region. By 2030, coal is forecast to supply about half of the electricity used by China’s AI data centers, while gas is expected to provide about 60% for US data centers.

Grid limits could slow new projects, the agency warned. In some regions, the combined capacity of data centers awaiting grid connections exceeds current peak demand. Congestion could make networks less reliable and force generators to cut output.

The IEA also cited tight supplies of copper, cables and transformers. Under its Current Policies Scenario, grid spending is projected to rise 75% over the next decade.

Topics
NGHGInternational Energy Agency
Further reading

This article was produced with the help of AI technology. Based on reporting by the outlets listed above.

Comments (0)

Log in to join the discussion.Log in

No comments yet - be the first to weigh in.