The company pushed back its revenue target timeline after a Microsoft-requested network redesign, while reporting higher AI cloud revenue.
IREN delayed some infrastructure deliveries for Microsoft and forecast about $15 billion in capital expenditure over the rest of its fiscal year. The company said the delay followed a Microsoft-requested network-design change and would not trigger financial penalties.
The shift also pushed back IREN’s timeline for reaching a more than $4 billion annualized run-rate revenue target. The company now expects to make the target operational in January, though timing could extend to the end of February because of the design change and supplier timing.
IREN reported first-quarter revenue of $228 million, above analysts’ average estimate of $221.28 million, according to LSEG data cited in the report. AI cloud revenue climbed to $200 million from $71 million in the previous quarter.
The company’s quarterly filing showed capital commitments of $18.95 billion at the end of September, compared with $13.81 billion three months earlier. GPU hardware on its balance sheet nearly tripled to $5.82 billion, while construction in progress stood at about $4.61 billion.
IREN executives said the company ended September with $1 billion in annualized run-rate revenue and expects roughly one-quarter of that to be recognized in the December quarter. As of 21:00 UTC on Nov. 5, IREN shares were at $18.03, down 16.95% from the previous close.