The company cited a customer-requested network change and supplier timing as it delayed its annualized revenue target and outlined $15 billion in spending.
IREN delayed the start of operations tied to its more than $4 billion annualized revenue target, shifting the timeline from year-end to January. The company said the delay could extend to the end of February and cited a customer-requested network change and supplier timing.
Co-CEO Daniel Roberts said Microsoft requested changes to network infrastructure for a 200-megawatt data center project. IREN said the change would not trigger financial penalties.
The company reported $228 million in revenue for the quarter ended September 30, above analysts’ $221.28 million estimate. AI Cloud revenue rose to $200 million from $71 million in the prior quarter, while net loss narrowed to $263 million from $684 million.
IREN plans about $15 billion in capital spending over the rest of its fiscal year. It said $9 billion would come from cash and committed financing, while another $6 billion is targeted financing subject to market conditions.
At Thursday’s close, IREN traded at $18.03, down 16.95% from the previous close. Shares rose in extended trading, according to the reports.