The cancelled data-center capacity deal highlights power and delivery risks as Nscale prepares for a potential public listing.
Microsoft has ended an agreement to lease computing capacity at Nscale’s data center in Essex, England, according to an analysis published by Expansión. The site is unlikely to receive power before 2030, the column said.
Nscale is seeking a New York listing at a reported $35 billion valuation. The cancelled deal covered a relatively small part of Microsoft’s spending with the company, but the analysis argues it exposes risks facing fast-growing AI cloud providers.
Nscale’s contracted revenue backlog exceeds $100 billion, according to the column, but delivering on those contracts would require 461,000 graphics processing units, nearly 20 times the number the company currently owns. The column also noted that Anthropic and Microsoft together account for close to 90% of the backlog, while some contracts allow customers to cancel if delivery milestones are missed.
The analysis said Nscale reported $141 million in revenue in the first half. If that growth pace continued through the rest of 2026, annual sales would reach $420 million, it estimated. Applying Nebius’s multiple to that figure would imply a valuation above $6 billion, the column said, and a lower figure using CoreWeave’s multiple.
The column argued that larger data-center operators could gain business if smaller providers cannot secure power, chips, financing and infrastructure in time. It also noted that Nscale had flagged several risks in its pre-IPO documents.
This article was produced with the help of AI technology. Based on reporting by the outlets listed above.