The Australian data center operator cut its revenue and EBITDA forecasts after community opposition delayed grid upgrades for its M3 site.
NextDC shares plunged 41.7% on Wednesday after the Australian data center operator cut its annual revenue and earnings forecasts. As of 5:17 UTC, the shares were at A$5.35, down 41.72% from the previous close.
The company now expects revenue of A$475 million to A$500 million, compared with its earlier forecast of A$615 million to A$640 million. It lowered its EBITDA forecast to A$245 million to A$265 million.
NextDC blamed delays to grid upgrades for its M3 Melbourne data center. It said electricity provider Jemena had suspended part of its network works, citing community opposition and a lack of local council consent while consultations continue.
NextDC also cut capital expenditure by A$750 million and put land acquisitions and new development projects on hold for the foreseeable future.