SK Hyper Seeks Funding for $350 Billion Data Centre Plan

Makkler Newsroom
October 23, 2026 · Based on reporting by The Business Times
Photo: PiDatacenters / Wikimedia Commons · CC BY-SA 4.0

The SK Group unit is discussing financing with technology companies and investors for a South Korea buildout planned through 2035.

Key takeaways

  • SK Hyper is seeking funding for a planned 15 GW data centre buildout in South Korea.
  • The first 5 GW phase is estimated to cost US$350 billion, including equipment.
  • SK Hyper aims to raise its first external capital by the end of 2026 or early 2027.

SK Hyper is in talks with technology companies and financial investors to fund a planned 15 gigawatts of data centre capacity in South Korea by 2035. The first 5 GW phase would cost US$350 billion, including equipment, CEO Chung Suk-geun told Bloomberg Television.

The company aims to secure its first external funding round by the end of 2026 or early 2027, then raise more capital over the following three to four years. SK plans to share the overall cost with data centre tenants and outside investors, Chung said.

Chung said the company would adjust investment to actual demand rather than commit to the full plan upfront. SK Hyper is seeking to attract global technology companies to South Korea to support AI training and operations for Asian markets including Japan and Taiwan.

The company is developing a 900-megawatt project in Ulsan alongside a previously announced 100 MW project for Amazon Web Services. It is also discussing additional sites with the government. Chung said SK Hyper could begin generating revenue as early as 2027, before its initial data centres are planned for completion in 2029.

Topics
017670AMZNSK HyperSK TelecomAmazon Web Services
Further reading

This article was produced with the help of AI technology. Based on reporting by the outlets listed above.

Comments (0)

Log in to join the discussion.Log in

No comments yet - be the first to weigh in.