Snowy Hydro’s cost target is $22 billion, with a further $3 billion allowance, and full operations are expected in late 2029.
Snowy Hydro’s latest review puts Snowy 2.0’s target cost at $22 billion, with up to $3 billion more available if needed. First power is expected in early 2029, and the project is forecast to be fully operational later that year.
The previous project reset had put the cost at $12 billion, with first power expected in late 2027. Chief executive Dennis Barnes said he was “incredibly disappointed” by the latest cost update and cited design immaturity before the reset as one factor.
The review found that 65% of machine tunnelling and 90% of cavern excavation had been completed. Work on the underground power station is underway, with 5,000 people now working on the project, according to Barnes.
Snowy 2.0 is designed to connect two dams through about 27 kilometres of tunnels and store electricity using pumped water. Barnes said he could not rule out further cost increases.
A separate economic study by consultant GHD estimated the project would contribute $18 billion to the Australian economy during construction and cut wholesale electricity costs by more than $7 billion by 2075.